  • Boertai Coal Preparation Plant, Wanli Coal Branch of China Shenhua Energy

    Construction scale: 31.00Mt/a. Project Category: EPC.

    Coal preparation process: Raw coal is separated by heavy medium shallow separator, and fine coal is recovered by pressure filter. The heavy medium system of final coal has been put into production. 

    2019-06-04
  • Coal Preparation Plant of Shanxi Pingyao Clean Coal Co., Ltd.

    Construction scale: 1.80Mt/aProject Category: EPC.  

    Coal preparation process: primary and secondary two-product dense medium cyclone for raw coal, coarse slime is separated by TBS separator and fine slime is separated by flotation machine. 


    2019-06-04
  • Shanxi Shuozhou Liujiakou Coal Preparation Plant

    Construction scale: 5.00Mt/a. Project Category: EPC. 

    Coal preparation process: raw coal is separated by two-product dense medium cyclone, coarse slime is separated by spiral separator and fine slime is recovered by filter press. 

    2019-06-04
  • Aury Banana Screen Series

    Aury Vibrating Screen applies equal thickness screening principle and linear vibration theory, adopts advanced design concept and advanced finite element force analysis and calculation method, manufactured with advanced numerical control processing equipment and technology, and advanced testing equipment, the product quality and performance have reached the advanced level in China. The design and manufacture of Aury Vibrating Screen meets the requirements of Australian standards and National standards. Welding of steel structures strictly follows the Australian AS1554.5 (Advanced Fatigue Load Welding of Steel Structures). Aury Vibrating Screen is mainly used for coal classification, desliming, dehydration and sculping. It is also suitable for screening and classification of other minerals.

    2019-06-04
  • Centrifuge

    It includes horizontal vibration centrifugehorizontal slime scraper discharging centrifuge vertical slime scraper discharging centrifuge. Centrifuge design mechanism is advanced, the main components are imported, product quality is reliable, is the best choice to replace imported equipment.

    2019-06-04
  • Slime Separator

    Working Principle: Feeding from slurry feeding pipe into the separator forms a suspension bed with a certain density. When it reaches a stable state, particles with a density lower than the average density of the bed will float and enter the float product. Particles with a density higher than the average density of the bed pass going through the bed and enter the sediment through the discharge port.  Product characteristics: The separator is a new type of equipment for separating coarse slime, and its particle size is between 0.25-1 mm. The amount of slime entering the flotation system is reduced, which not only saves the dosage of flotation reagents, but also reduces the load of the slime water system and improves  the final clean coal production of the coal preparation plant..

    2019-06-04
  • 34.00Mt/a Daliuta Coal Preparation Plant of Shenhua Shendong Group

    Construction scale: The production capacity of coal preparation plant is 34.0Mt/a.Coal preparation process: 200-13mm lump coal is separated by 6mm wet dewatering and 200-6mm heavy medium shallow separation. The 13-0mm final coal is further separated by the 6(5)mm dry method, and the 13-6(5)mm final coal is separated by the pressurized two-product heavy medium cyclone, and the 6(5)-0mm final coal is directly mixed into the product. The 1.5-0.2mm coarse coal slurry entering the system is separated by a spiral separator, and the - 0.2mm slime is recovered by a filter press.

    2019-06-04
  • SDIC Hami No. 1 Coal Minie Coal Preparation Plant

    Construction scale: 12.0Mt/a. Coal preparation process: 150-13mm lump coal washed, -13mm fine coal not washed, and the -13mm coal washing interface is reserved; slurry in lump coal washing system is treated separately by coarse slime and fine slime, 3-0.25mm coarse slime is dewatered and recovered by slime centrifuge and - 0.25mm fine slime is dewatered and recovered by fast-opening diaphragm filter press.

    2019-06-04

About Us

Dadi Engineering Development (Group) Co., Ltd. (hereinafter referred to as Dadi Company) was established in 1995. It was a Sino-Australian joint venture approved and registered by the former Ministry of Foreign Trade and Economic Cooperation of China, and belonged to the former Ministry of Coal Industry. In 2007, Reform into a joint stock company with a registered capital of 110.068609 million yuan.